For some organizations, resources costs are primary costs, and sometimes the only cost, so these need to be closely monitored.
![resource cost](https://images.edrawsoft.com/images2019/guide/edrawproject/resource-cost1.png)
Task Work
In the Task Work report, the time amount of total work, actual work, and remaining works are displayed for all sub-tasks.
The following are formulas to calculate different types of cost:
- Actual Work = Progress*Work
- Remaining Work = (1 - Progress) * Work