Edraw Centre de Soutien
Obtenez des réponses rapides et des instructions étape par étape.
Critical Tasks
It has to be clear that the word “Critical” does not mean that the task is complex, important or need to be closed, monitored, but the focus is that the task will affect the project's finish date.
Delay Tasks
In the Delay Tasks report, Tasks that have been delayed in comparison with the current date are displayed.
Behind Tasks
If a task’s completion date exceeds its baseline finish date, then it is a Behind Task.
Click the Behind Tasks button on the Reports tab to view the report of behind tasks in the project.